Resource Process - Produce Styrene from Ethylene

Characteristics

AttributeValue
Process Time:200 millisols
Work Time:10 millisols
Power Required:0.05 kW/hr
Start On:false

Inputs

NameInput Rate (kg/sol)Minimum kgAmbient
Carbon32.120.002false
Ethylene8.340.0false
Water16.050.001false
Lime2.00.0false

Ambient inputs are consumed from the environment.

Outputs

NameOutput Rate (kg/sol)Waste Output
Styrene30.95false
Carbon monoxide24.97false

Waste outputs are released into the environment and do not need to be stored.

Version: 3.10.0 Generated on: 2025-10-09T21:45:01.8754429